We have reached a new milestone in the WRF construction as portions of the project are going vertical! The contractor is forming the walls for the treatment tanks, installing the block wall for the disinfection building, and preparing to place the concrete footing for the headworks building.
- 2,144 yards (of 15,000 total yards) of concrete has been poured.
- Approximately 300 tons of reinforcing steel has been placed.
- The project is approximately 8% complete and should be operational by July of 2025.
Check out some the project photo album.