2300 E Canyon Road (SR-198) Traffic Signal Update
Which parties are involved in getting a traffic signal at this intersection?
- Canyon Road (SR-198) is owned & maintained by UDOT
- 2300 E is owned & maintained by Spanish Fork City
Who can authorize that a traffic signal be placed at this intersection?
- Because a UDOT road is part of this intersection, the City must receive approval through UDOT’s permitting process
What is the timeline that has been and will be followed for this project?
- Spring 2022 North Leg of 2300 E Canyon Rd intersection completed.
- August 2022 Signal Warrant Study completed
- First quarter 2023 Spanish Fork agrees to have it designed and constructed with a reimbursement agreement from UDOT to speed up the project
- Fall 2023 plans approved by UDOT
- April 2024 UDOT final approval for construction
- Project Bids due in May
- Construction complete by August 2024
What is being done in the meantime to improve safety at this intersection?
- Pedestrian detour signs directing pedestrians to cross at Spanish Fork Parkway will be placed at the intersection
- A speed trailer has been placed at the intersection
- North leg of the intersection will be closed throughout construction
- Other safety measures are being evaluated
At a City Council meeting a resident stated that the City received money from UDOT a year ago to complete this project. Is this true?
- No, this is not true
- The City is fronting the cost for this project. Once the project has been completed, UDOT will reimburse the City