REC CENTER CONSTRUCTION UPDATE - October 2024
Spanish Fork, UT — Great progress is being made on the Spanish Fork recreation, aquatic, and community/senior center!
The construction of the building is split into three areas, A, B, and C. Area A includes the locker rooms and indoor pool area - excluding the competition pool. Area B includes the competition pool, boiler, electrical, and chemical storage. Area C includes the community/senior center, multipurpose gym, fitness area and track, and administrative offices.
Structure Updates
Area A:
- Pool Piping and Footings nearing completion.
- Duct work is currently being installed.
- Mason is finishing the veneer behind the dive pool.
- Stairs behind dive pool will start end of the month.
Area B:
- Overhead electrical in progress.
- Tnemec steel painting will start in the next 1-2 weeks.
- Fire Sprinkler lines starting over bleachers.
- Roofing work has begun.
Area C:
- Structural Steel and decking in progress.
- Metal Soffit framing has started.
- Structural Masonry is nearly complete.
Timeline Updates
The project is still on track for a Fall 2025 opening!