Spanish Fork Rec Center - October 2024 Update

REC CENTER CONSTRUCTION UPDATE - October 2024


Spanish Fork, UT — Great progress is being made on the Spanish Fork recreation, aquatic, and community/senior center!

The construction of the building is split into three areas, A, B, and C. Area A includes the locker rooms and indoor pool area - excluding the competition pool. Area B includes the competition pool, boiler, electrical, and chemical storage. Area C includes the community/senior center, multipurpose gym, fitness area and track, and administrative offices.

Structure Updates

Area A:​

- Pool Piping and Footings nearing completion.​

- Duct work is currently being installed.​

- Mason is finishing the veneer behind the dive pool.​

- Stairs behind dive pool will start end of the month.

 

Area B:​

- Overhead electrical in progress.​

- Tnemec steel painting will start in the next 1-2 weeks. 

- Fire Sprinkler lines starting over bleachers.​

- Roofing work has begun.

 

Area C:​

- Structural Steel and decking in progress.​

- Metal Soffit framing has started.​

- Structural Masonry is nearly complete. 

 

 

Timeline Updates

The project is still on track for a Fall 2025 opening!