Spanish Fork, UT — Even with the cold weather, a lot of progress is being made on the Spanish Fork recreation, aquatic, and community/senior center!
The construction of the building is split into three areas, A, B, and C. Area A includes the locker rooms and indoor pool area - excluding the competition pool. Area B includes the competition pool, boiler, electrical, and chemical storage. Area C includes the community/senior center, multipurpose gym, fitness area and track, and administrative offices.
Structure Updates
Area A:
- Overhead work nearing completion.
- Dive pool structure concrete platform poured.
- Roofing membrane installation nearing completion.
- Tnemec steel painting will start soon.
Area B:
- Tnemec steel painting in progress.
- Backfill completed behind competition pool
Area C:
- Structural Steel and decking nearing completion.
- Preparing to start roofing.
- Structural steel running track ongoing.
- Exterior framing and sheathing ongoing.
Site Work:
- Outdoor pool plumbing work in progress.
- Outdoor program pool floor in progress
Timeline Updates
The project is still on track for a Fall 2025 opening!