Spanish Fork, UT — Even with the rain and snow, good progress is being made on the Spanish Fork recreation center!
The construction of the building is split into three areas, A, B, and C. Area A includes the locker rooms and indoor pool area - excluding the competition pool. Area B includes the competition pool, boiler, electrical, and chemical storage. Area C includes the community/senior center, multipurpose gym, fitness area and track, and administrative offices.
Structure Updates
Area A:
- Tnemec Paint to start in a 2 weeks
- Window Frames are currently being installed
- Dive Pool Stairs are poured
- Roofing is complete
Area B:
- Pool plumbing & backfill nearing completion
- Tnemec painting is complete
- Exterior Framing is complete
- Window Frames installed
Area C:
- Steel deck will be complete this week
- Structural steel running track is being installed
- Exterior soffit framing ongoing
- Started interior framing of walls
- All slab on decks have been poured, excluding running tracks
- Roofing installation nearing completion
- Pump House pool piping installation ongoing
- Concrete curb and gutter poured in parking lot
- Pavilion and Pump House foundations complete