REC CENTER CONSTRUCTION UPDATE - February 2025

Spanish Fork, UT — The Spanish Fork FitCity Center continues to move forward towards completion this fall. A lot of work is happening every day inside and outside the building.

The construction of the building is split into three areas, A, B, and C. Area A includes the locker rooms and indoor pool area - excluding the competition pool. Area B includes the competition pool, boiler, electrical, and chemical storage. Area C includes the community/senior center, multipurpose gym, fitness area and track, and administrative offices.


Structure Updates

Area A:​

  • MEP Rough is complete​
  • Tnemec Paint is starting on Monday 2/17​
  • Exterior Glass is currently being installed

Area B:​

  • Pool backfill complete
  • Bottom of pool plumbing in progress​
  • Prepping to pour pool slabs next week​
  • Metal Panels are being install​
  • Glass installation complete

Area C:​

  • Finishing Steel upper track today​
  • Pouring upper track slab on deck next week​
  • MEP rough on-going ​
  • Admin Area stud framing complete​
  • Community Center Area stud framing in progress​
  • Waterproofing exterior soffits​
  • Main roof membrane is complete ​
  • Installing membrane on lower roofs

Site Work:

  • Backfilling underground pool piping ​
  • Road Base laid at SW parking lot​
  • Installing light pole bases

Timeline Updates

The project is still on track for a late fall 2025 opening.


Photos

February 2025 Rec Center Photos