Spanish Fork, UT — The Spanish Fork FitCity Center continues to move forward towards completion this fall. A lot of work is happening every day inside and outside the building.
The construction of the building is split into three areas, A, B, and C. Area A includes the locker rooms and indoor pool area - excluding the competition pool. Area B includes the competition pool, boiler, electrical, and chemical storage. Area C includes the community/senior center, multipurpose gym, fitness area and track, and administrative offices.
Structure Updates
Area A:
- MEP Rough is complete
- Tnemec Paint is starting on Monday 2/17
- Exterior Glass is currently being installed
Area B:
- Pool backfill complete
- Bottom of pool plumbing in progress
- Prepping to pour pool slabs next week
- Metal Panels are being install
- Glass installation complete
Area C:
- Finishing Steel upper track today
- Pouring upper track slab on deck next week
- MEP rough on-going
- Admin Area stud framing complete
- Community Center Area stud framing in progress
- Waterproofing exterior soffits
- Main roof membrane is complete
- Installing membrane on lower roofs
Site Work:
- Backfilling underground pool piping
- Road Base laid at SW parking lot
- Installing light pole bases
Timeline Updates
The project is still on track for a late fall 2025 opening.