REC CENTER CONSTRUCTION UPDATE - March 2025

Spanish Fork, UT — Spring is around the  corner and site work is being done at the Spanish Fork FitCity Center to get the parking lot and landscaping ready to be installed. Progress is made each day towards completion this fall.

The construction of the building is split into three areas, A, B, and C. Area A includes the locker rooms and indoor pool area - excluding the competition pool. Area B includes the competition pool, boiler, electrical, and chemical storage. Area C includes the community/senior center, multipurpose gym, fitness area and track, and administrative offices.

Structure Updates

Area A:​

  • Tnemec Paint nearing completion​
  • Pool Structure work ongoing​
  • Exterior Metal Panels currently being installed

Area B:​

  • Pool deck concrete in progress​
  • Bottom of pool concrete poured​
  • Exterior Metal Panels complete​
  • Exterior glass complete

Area C:​

  • Upper Track concrete complete​
  • MEP rough in progress ​
  • Metal stud framing work ongoing​
  • Waterproofing exterior soffits nearing completion​
  • Installing membrane on lower roofs

 

Site Work:

  • Site Concrete work in progress​
  • Pavilion Steel is being installed​
  • Pump House Masonry nearing completion

Timeline Updates

The project is still on track for a late-fall 2025 opening.

Photos

March 2025 Rec Center Photos